– Operation of two cranes
– Installation of the steel structure, including bracings and Venlo gutters
– Connection of support bases using wood screws and formwork dowels
– Installation of aluminum structures and roof glazing
– Installation of aluminum structures and façade glazing
– Installation of aluminum structures and intermediate wall glazing
– Installation of all flashings and sheet metal works
– Installation of the collecting gutter along axis 8
– Installation of substructures for doors and gates
– Installation of louver windows (“Lamellenfenster”)
– Installation of the wooden plinth, including thermal insulation
– Installation of roof drainage downpipes
– Assembly of ventilation flaps
– Installation of ridge and façade ventilation windows, including special drive systems
– Setup and adjustment of limit switches
– Installation of substructures for stair tower netting
– Unloading and on-site handling of materials